Highways improvements outside Northampton International Academy

19 June 2018

To accommodate the new Northampton International Academy, highways improvements are needed outside the Barrack Road site. 

The improvements will result in better accessibility and safety for pupils and parents and will also benefit road users.

New traffic signals will feature the latest method of control which will help improve congestion and flow within the area by detecting pedestrian movement and queuing traffic.

The works are being carried out by Northamptonshire Highways on behalf of the Northampton International Academy and need to be completed prior to the Academy opening in September 2018.

Traffic Management Information (dates subject to programme change)

Phase One – Lane one closure to complete eastern footway.
18 June – 6 July, 2018. Three weeks.

Phase Two – Centre lane closures inbound and outbound to complete all works within the central parts of the carriageway.
9 July – 20 July, 2018. Two weeks

Phase Three – Lane one closure to complete western footway (two weeks). Closure of Adelaide Street (one week).
23 July – 10 August, 2018. Three weeks total.

Phase Four – two-way signals/ road closure Adelaide Street 8:00pm – 6:00am. Night works for resurfacing, road markings and traffic signal detection loops.
13 August – 17 August, 2018. One week.

Additional signage will be placed in the area to ensure that people are aware that businesses are still open. Pedestrians will be diverted safely around the works area to keep access to local businesses